LEED Existing Building (EB) Projects
PDF – 2BGW LEED Projects Energy Savings Equivalents
2BGW LEED EB Case Studies – March 2011
100 North Tampa
Building Gross Square Feet: 590,947
LEED Certification: EBOM – Silver, October 2009
Total Costs: $115,000 (Oct. 2009)
Energy Savings: $225,000 – 2010 vs. 2009
Water Savings: 2.4 million gallons – 2010 vs. 2009
Avg. Recycling Amount: 990,000 lbs/year of “ongoing consumables”
2525 Ponce de Leon
Building Gross Square Feet: 263,118
LEED Certification: Gold, LEED EB v2008, Sept. 2010
Total Costs: $79,000
Energy Savings: $121,195 – 2010 vs. 2009 costs
Water Savings: (19,111) gallons, $16,000 – 2010 vs. 2009 costs
Avg. Recycling Amount: 246,000 pounds/year of “ongoing consumables”
2555 Ponce de Leon
Building Gross Square Feet: 112,711
LEED Certification: Silver, LEED EB v2008, Sept. 2010
Total Costs: $60,000
Energy Savings: $70,500 – 2010 vs. 2009 costs
Water Savings: (1,189) gallons, $9,300 – 2010 vs. 2009 costs
Avg. Recycling Amount: 152,844 pounds/year of “ongoing consumables”
Waterford Plaza
Building Gross Square Feet: 275,217
LEED Certification: Certified, LEED EB v2009, May. 2011
Total Costs: est. $30,000
Avg. Energy Savings: est. $20,000/year
Avg. Water Savings: $3,000/year; 30,000 gallons/year
Avg. Recycling Amount: 300,000 Pounds/Year; 25,000 Pounds/Month
Island Center
Building Gross Square Feet: 279,311
LEED Certification: Certified, LEED EB v2009, May. 2011
Total Costs: $30,000
Avg. Energy Savings: $25,000/year
Avg. Water Savings: $2,000/year, 40,000 Gallons/year
Avg. Recycling Amount: 300,000 Pounds/Year; 25,000 pounds/month
LEED EB Projects in Process
Westside Plaza 1, 2, & 3
Buildings Gross Square Feet:
WP1 – 153,365;
WP2 – 108,980;
WP3 – 108,980
LEED Certification: LEED EB v2009, Phase I – Feasibility Study
Estimating Basic to Silver Certification for all 3 projects
Total Costs: Estimating $30,000 per project
Avg. Energy Savings: Estimating $20,000 – $35,000/year per project
Avg. Water Savings: Estimating 50,000 Gallons/Year per project
Avg. Recycling Amount: Estimating 180,000 Pounds/Year per Project